Central Vietnam province Quang Tri adjusts two wind power projects worth nearly $140 mln
Quang Tri province authorities have approved adjustments to the investment plans and investors for the TNC Quang Tri 1 and 2 wind power plant projects, with a combined capacity of 100 MW and total investment capital after the adjustments exceeding VND3.63 trillion ($139.97 million).
Under the adjustment decision issued by the provincial People’s Committee, TNC Quang Tri 1 Wind Power JSC is the investor of the TNC Quang Tri 1 Wind Power Plant, which has a capacity of 50 MW and is expected to generate about 128.48 million kWh of electricity annually.
The project will use about 32.5 hectares of land, including 17.5 ha of land allocated for a fixed term and 15 ha for temporary use. Total investment capital has been increased to VND1.81 trillion ($69.77 million), including VND362 billion contributed by the developer and nearly VND1.45 trillion in mobilized capital.
TNC Quang Tri 2 Wind Power Joint Stock Company is the investor of the TNC Quang Tri 2 Wind Power Plant, which has a capacity of 50 MW and is expected to generate 128.83 million kWh of electricity annually.
The project will also use about 32.5 hectares of land, with total investment capital after the adjustment set at VND1.821 trillion ($70.2 million), including VND364.2 billion in investor-contributed capital and nearly VND1.46 trillion in mobilized capital.
The two projects have a combined expected annual electricity output of about 257.31 million kWh.
Quang Tri initially gave in-principle approvals to both projects in 2020, with adjustments made in July 2022 and September 2025.
Under the initial investment plan, TNC Quang Tri 1 had a capacity of 50 MW and was expected to use 22.37 hectares of land, including 17.37 hectares of land for fixed-term use and 5 hectares for temporary use, with total investment capital of more than VND1.805 trillion ($69.6 million).
Meanwhile, TNC Quang Tri 2 also has a capacity of 50 MW, with a planned land area of 22.37 hectares, including 17.37 hectares of land for fixed-term use and 5 hectares for temporary use. The project's initial total investment was more than VND1.167 trillion ($44.99 million).
Following several adjustments, total investment capital for TNC Quang Tri 1 and 2 increased to VND1.81 trillion ($69.77 million) and VND1.821 trillion ($70.2 million), respectively.
At the same time, the planned land area for each project increased from 22.37 hectares to 32.5 hectares, mainly due to an increase in temporary land use from 5 hectares to 15 hectares.
Previously, in July 2026, Quang Tri province also adjusted the investment plan for the SCI Tan Thanh Wind Power Plant, invested by SCI Quang Tri JSC. The project's investment capital was increased to VND1.83 trillion ($70.58 million), while its capacity was raised from 30 MW to 42 MW and its scheduled operation was pushed back to the end of 2027.
Beyond delays, the investor selection process has also exposed several shortcomings. The Quang Tri provincial Inspectorate said 13 of 14 wind power projects had their requests for expressions of interest approved without sufficient legal grounds regarding land, while five projects lacked detailed planning schemes or zoning plans at a scale of 1:2,000 at the time of approval.
Some dossiers also applied investor experience criteria that were not in line with regulations, potentially affecting competition and transparency.
However, the provincial Inspectorate assessed that the projects were consistent with the Power Development Plan VIII and other relevant planning schemes, and found no signs of policy abuse or serious violations by the investors.
It recommended that relevant agencies draw lessons from the issue and review applicable regulations to ensure that energy projects are implemented in accordance with the required procedures in the future.
Source: Dinh Duy, Minh Hue
